Highgate revamp to run into the new year (From The Westmorland Gazette)
When news happens, text KENEWS and your photos and videos to 80360. Or contact us by email or phone.
Highgate revamp to run into the new year
9:00pm Wednesday 24th October 2012 in News
A KENDAL regeneration scheme, which should have been completed by Easter, is set to drag into the new year.
There were fears the £345,000 Highgate project, which started in September after a five-month delay, could have run until late November, hitting Christmas trade. But the construction team will down tools on November 9, and not go back on site until January.
South Lakeland district councillor, and Highgate Partnership member Coun Graham Vincent slammed the delay and its effect on trade. He said: “There doesn’t seem to be much understanding of what businesses’ fears are.”
It is understood bad weather and extra materials needed for new traffic lights have prolonged the work.
Emma Butterworth, 33, who owns the Frothimoon bridal shop, said the work had already had a ‘massive affect’ on her business.
Cumbria County Council said: “Highgate works have been extended but, rather than run into the Christmas shopping season, we will halt works on November 9, and then the Christmas embargo period will begin. The works will be picked back up in January.”
Comments(15)
oceancloud
says...
9:50pm Wed 24 Oct 12
Lakeuk
says...
12:04am Thu 25 Oct 12
Had a wonder through K Village a couple of weeks bad, bit shocking to see the woodwork and paint peeling a way, they need a maintain guy to look after the up keep. If they're not paying money on maintainable then not much chance of Kendal getting it's promised £100k
adecco12
says...
2:14pm Thu 25 Oct 12
Moonbase
says...
7:23pm Thu 25 Oct 12
I suppose we have one consulation.......
Extra yellow flashing lights as you crawl through town at christmas...unfortun
ately they are not christmas lights just road work lights.
As for the 100k...there was no way that was ever going to be paid and as for the museum...........the whole debarcle is going to turn into one anyway by itself.
Could'nt make it up.....well you could..
Seriously,a factory outlet with no parking for coaches.
Bright!!!!!!
Moonbase
says...
7:26pm Thu 25 Oct 12
oceancloud wrote:Heard there is 'Mice' in 224........
Not much sign of any re generation going on at the moment. Just the generation of huge traffic jams coming into the town! Cannot honestly think that any funds will be forthcoming from K Village. I find it a novelty to stop at the traffic lights and see the odd car emerging. Cadbury's are/have pulled out and I'me sure there will be more to come before long. I understand there is not one of the flats occupied.
Kendaltrader
says...
11:18am Fri 26 Oct 12
whiskeydelta
says...
3:27pm Fri 26 Oct 12
Ambience
says...
10:48am Sat 27 Oct 12
Milkbutnosugarplease
says...
3:32pm Sun 28 Oct 12
life cycle too
says...
9:46am Mon 29 Oct 12
However, their road improvement scheme along the lines of the Highgate scheme looked like it was designed as a junior school project!
newcmr
says...
7:59pm Mon 29 Oct 12
Desdan
says...
7:54pm Tue 30 Oct 12
Kendaltrader
says...
9:05am Wed 31 Oct 12
snuggle-bunny
says...
10:25pm Wed 31 Oct 12
TomHarvey says...
9:43pm Wed 24 Oct 12
We are also still waiting for the £100k+ that should have come from K-Village as part of their agreement to develop the Shopping Village which was to support this, instead taxpayers are footing that part of the bill until (if) they pay up.